Ironworks: closed out +$312K vs. estimate; concrete & framing actuals added to the cost database.
Cedar Ridge: on schedule; gym roof dry-in Jul 24 is this week's critical milestone.
Meridian: RFI #041 aging 12 days with the architect; structural steel release is now the critical path.
Bayview: bid day in 23 days; sub coverage still thin in electrical, roofing, and elevators.
Schedule: Level 4 framing finished Thursday, 3 days early. Top-out is now trending 6 days ahead of baseline. Window package delivery confirmed for Aug 3; dry-in milestone holds only if scaffold inspection passes Thursday. View source ↗
Pending approvals (2): ① Unit finish upgrade option for floors 5–6: sub needs direction by Wed to hold framing sequence; est. impact +$41K, zero schedule cost if decided this week. ② RFI #027 (podium waterproofing detail at grid C) has sat 9 days with the architect, and every day past Friday consumes schedule float. View source ↗
Cost: Concrete closed out $63K under estimate (early buyout). Electrical rough-in trending $28K over on unit metering change events; PM notes cause is a design revision, recoverable as CO. Net margin position improved $35K this week. View source ↗
Field notes worth reading: Superintendent flagged repeated after-hours water intrusion at the north excavation, third mention in 18 days of log entries. Pattern surfaced automatically; may warrant a dewatering review before slab pour. View source ↗
| Division | Estimate | Projected | Δ |
|---|---|---|---|
| 03 Concrete ↗ | $3.41M | $3.35M | −$63K |
| 06 Wood framing ↗ | $4.86M | $4.84M | −$22K |
| 26 Electrical ↗ | $2.92M | $2.95M | +$28K |
| 22 Plumbing ↗ | $2.31M | $2.30M | −$8K |